The following PMP® exam sample question is taken from the Free PMP Exam Simulator:
------------------------------
In your project, you can delay 'Activity 1' by three days without delaying its successor 'Activity 2'. However, delaying 'Activity 1' will delay the project by six days without delaying the overall project finish date. Which of the following statements is correct in this scenario?
A.) The Total Float is 6 days and the Free Float is 3 days.
B.) The Total Float is 3 days and the Free Float is 6 days.
C.) The Total Float is 3 days and the Free Float is zero.
D.) The Free Float is 3 days and the Total Float is zero.
------------------------------
Hint: Don’t get confused with Free Float versus Total Float. Remember Total Float always applies to project and Free Float applies to individual activities.
------------------------------
All our questions are updated to the latest PMBOK® Guide standard. Stop by at http://free.pm-exam-simulator.com and try the PMP Exam Simulator free for 3 days. We also offer 110 free questions at http://www.free-pm-exam-questions.com. We are a PMI Registered Education Provider.
Please click here:http://www.facebook.com/PrepCast for the correct answer and explanation.