Sponsor: Level 5 Partners, Inc.

  News

  Forums
Project Portfolio Management
Product Lifecycle Management
Portfolio Management
Program Management Office
Project Management
Project Management - General
Risk Management
Schedule Management
Scope Management
Requirements Management
Project Management in Education
Careers
Job Postings
PMs For Hire
PM Certification
Standards
Methodologies
Best Practices

  Events

  Resources

  About the Network

Free PMP Exam Sample Question
[Logo]
  [Search] Search   [Recent Topics] Recent Topics   [Hottest Topics] Hottest Topics   [Members]  Member Listing   [Groups] Back to home page 
[Register] Register / 
[Login] Login 
Free PMP Exam Sample Question  XML
Forum Index » PM Certification
Author Message
[Post New]04/12/2011 04:27:16
    Subject: Free PMP Exam Sample Question
[Up]
ospinternational


Joined: 08/03/2010 12:04:53
Messages: 189
Offline

The following PMP® exam sample question is taken from the Free PMP Exam Simulator at http://free.pm-exam-simulator.com - The answer is at the very bottom:

------------------------------

You are managing a water supply network deployment project. During project planning you are considering two approaches to lay the pipe network. Approach A will most likely cost $50,000 (±5%). Approach B will most likely cost $25,000 (±40%). Which approach will you select if your project stakeholders' risk tolerances are low and if you want to select the less risky approach?

A.) Neither approach since they are not definitive estimates.
B.) Approach B since it ranges from $15,000 to $35,000.
C.) Approach A since it ranges from $47,500 to $52,500.
D.) A combination of approach A and B.

------------------------------
Hint: Estimates are never definitive.
------------------------------

All our questions are updated to the latest PMBOK® Guide standard. Stop by at http://free.pm-exam-simulator.com and try the PMP Exam Simulator free for 3 days. We also offer 110 free questions at http://www.free-pm-exam-questions.com. We are a PMI Registered Education Provider.


Until next time,
Cornelius Fichtner, PMP
President, OSP International LLC
The Project Management PrepCast™ - http://www.project-management-prepcast.com
The Project Management Podcast™ - http://www.project-management-podcast.com


ANSWER AND EXPLANATION:
The correct answer is C
Explanation: Please note that the question doesn't ask for the approach that is more financially feasible. Instead, the question asks you to identify the approach that has the lower risk. The larger the range of an estimate, the larger the risk. Since approach B is a wide range estimate, it is more risky. Approach C has a narrow estimate, which makes this approach less risky.
Reference: PMBOK Guide 4th Edition, page 284