Sponsor: Level 5 Partners, Inc.

  News

  Forums
Project Portfolio Management
Product Lifecycle Management
Portfolio Management
Program Management Office
Project Management
Project Management - General
Risk Management
Schedule Management
Scope Management
Requirements Management
Project Management in Education
Careers
Job Postings
PMs For Hire
PM Certification
Standards
Methodologies
Best Practices

  Events

  Resources

  About the Network

Free PMP Exam Sample Question
[Logo]
  [Search] Search   [Recent Topics] Recent Topics   [Hottest Topics] Hottest Topics   [Members]  Member Listing   [Groups] Back to home page 
[Register] Register / 
[Login] Login 
Free PMP Exam Sample Question  XML
Forum Index » PM Certification
Author Message
[Post New]29/10/2011 05:10:58
    Subject: Free PMP Exam Sample Question
[Up]
ospinternational


Joined: 08/03/2010 12:04:53
Messages: 189
Offline

The following PMP® exam sample question is taken from the Free PMP Exam Simulator at http://free.pm-exam-simulator.com - The answer is at the very bottom:

------------------------------

What is risk tolerance?

A.) Risks created by tolerating customer behavior.
B.) Willingness to accept varying degrees of risk.
C.) Risks created by zero tolerance.
D.) Being tolerant if stakeholders are willing to accept risks.

------------------------------
Hint: Look for the “least strange” answer.
------------------------------

All our questions are updated to the latest PMBOK® Guide standard. Stop by at http://free.pm-exam-simulator.com and try the PMP Exam Simulator free for 3 days. We also offer 110 free questions at http://www.free-pm-exam-questions.com. We are a PMI Registered Education Provider.

Until next time,
Cornelius Fichtner, PMP
President, OSP International LLC
The Project Management PrepCast™ - http://www.project-management-prepcast.com
The Project Management Podcast™ - http://www.project-management-podcast.com


ANSWER AND EXPLANATION:
The correct answer is B
Explanation: Do you feel that A, C and D are odd? Correct, they are and they were included intentionally. Sometimes you can expect to find some “funny” answer choices.
Risk tolerance is the stakeholders' willingness to accept varying degrees of risk. Choice B is the only correct answer to this question.
Reference: PMBOK4 - pg:276